AHU Flat Pack Install – Call Centre Milton Keynes

CLP Air Group successfully installed a 7.0m³/s heat recovery AHU and two smaller units through a restricted 1000mm x 1000mm access opening. Expert planning, precision engineering, and a three-day installation ensured a seamless, high-efficiency solution.

Project Overview

A client approached CLP Air Group with a unique challenge: Can you fit a 7.0m³/s heat recovery AHU, along with two smaller units, in a plant room via a restricted 1000mm x 1000mm access opening—followed by a two-metre drop to the plant room floor?

Our answer: Yes, we can!

 

Meeting the Challenge

With such tight access constraints, a fully flat-pack installation was the only viable solution. Our engineers carefully planned and executed the delivery, ensuring all AHU components could be safely manoeuvred through the restricted entry point and reassembled on-site.

 

AHU Specifications

AHU 1 – Main Supply & Extract Heat Recovery Unit

  • Airflow: 7.0m³/s
  • Features:
    • Thermal wheel heat recovery
    • LPHW heating
    • DX heat pump coil
    • Direct-driven multi-fan wall EC fans
    • Full energy-efficient controls
    • Fully segmented and split-casework thermal wheel for restricted access

AHU 2 – Supply Only Unit

  • Airflow: 1.5m³/s
  • Features:
    • LPHW heating
    • DX heat pump coil
    • Direct-driven EC fan
    • Full energy-efficient controls package

AHU 3 – Supply & Extract Heat Recovery Unit

  • Airflow: 0.8m³/s
  • Features:
    • Plate heat exchanger for heat recovery
    • LPHW heating
    • DX heat pump coil
    • Direct-driven EC fans
    • Full energy-efficient controls package

 

Innovative Design and Installation

  • Careful Crane Lift Management:

    • Our engineers supervised the crane lift, ensuring all AHU components were landed in the correct sequence for efficient assembly.
    • Close coordination with the client and crane company minimised risks and ensured a smooth process.
  • Precision Installation:

    • The challenging site conditions required expert handling, with all components passed through the restricted access opening.
    • The installation was completed within just three days by our in-house team, demonstrating our efficiency and expertise.

 

Results

This complex AHU installation was successfully delivered, overcoming significant logistical challenges. Our expert planning, engineering precision, and high-quality workmanship ensured the project was completed on time, with minimal disruption and maximum efficiency.

 

Client feedback

“CLP Air Group handled this difficult installation with absolute professionalism. Their ability to navigate tight access constraints while maintaining excellent build quality was outstanding. We are thoroughly impressed with the outcome.”